Success of Hot Commissioning of Jilin Steel 1450mm Hot Rolling Project
2011-07-12 09:01:17
Tapping of RHF
Successful Hot Commissioning
Successful Hot Commissioning
The hot commissioning of Jilin Jianlong Steel 1450mm Hot Rolling Project which engineered by CISDI gets success on April 30th 2011, and the #1 reheating furnace contracted by CISDI on EPC basis is previously heated up on April 8th. On the other hand, the construction of #2 reheating furnace is going smoothly and the water treatment system is to be put into operation after the hot commissioning of hot rolling line.
The Jigang Steel 1450mm hot rolling line with annual output of 3.00Mt is undertaken by CISDI in 2007 with responsibilities covering plant engineering, technical support and EPC of reheating furnace and water treatment system. Overcoming difficulties such as tight schedule, lag period and severe weather, CISDI provides satisfactory and timely technical supports and services, which gains fully affirmations from the Owner.