January 12, 2011, reheating furnace for bar mill of Handan Steel, Hebei Steel Group was successfully drying-off under turnkey operation of CISDI. On January 30, 2011, the walking-beam bar mill RHF delivered the 1st heated billet, and matched with rolling mill for completing the process, which was satisfactory to the customer. On the same day, the walking-beam RHF for wire rod mill was drying-off.
Contract Signoff
|
Mar.12, 2010
|
|
Main Product & Specification
|
Bar: building bar, quality bar (quality carbon structural steel, alloy structural steel, spring steel, bearing steel, cold upset steel), specifications in Ф16~80mm
|
Wire-rod: plain carbon steel, quality carbon steel (quality carbon structural steel, welding wire, spring steel, bearing steel, cold upset steel), specifications in Φ5.0~22mm
|
Heating Capacity
|
Bar: 170t/h (800,000t/a)
|
Wire-rod: 150t/h (700,000t/a)
|
Annual Output
|
Bar: 833,330 t
|
Wire-rod: 729,160t
|